PUNJAB ROAD SECTOR PROJECT (PHASE-II PACKAGE-XIV-B)

 

 

CONSULTANT
M/s Consulting Engineering Services (India) Pvt. Ltd. New Delhi
DATE OF CONTRACT
17th January 2011
TIME PERIOD
Phase I - 3 months
Phase II - 5 Months
MAIN TASKS OF THE CONSULTANCY SERVICES
(Phase - I and Phase II)
Part A: Carry out Average network speed (kmph), Vehicle Operating Cost (and all associated surveys) and Traffic surveys on core network of 1696 kms of road length. Baseline for this would be data from feasibility report. This length remains same for baseline, midterm and end term surveys.
Phase - I
Part B: Condition and roughness surveys to be carried out on approx 705 kms of road length which has been constructed/ maintained in Phase I of PSRSP. Baseline for this would be data from feasibility report for those project roads which are listed in core network but for other roads the baseline data would be respective DPRs. The Consultant shall compare the results with baseline surveys conducted in year 2005 under Phase I of this project or the data available for completed works as the case may be.
Phase II
Part B: Condition and roughness surveys to be carried out on approx 705 kms of road length which has been constructed/ maintained in Phase I of PSRSP and approx. 950 km roads under OPRC (Phase II of PSRSP). Baseline for 705 km would be data from feasibility report for those project roads which are listed in core network but for other roads the baseline data would be respective DPRs. The Consultant shall compare the results with midterm surveys conducted in year 2010 or the data available for completed works as the case may be.
 
 
 

 

 
 