Punjab State Road Sector Project Division FEROZEPUR
Construction Division No. 3, PWD B & R, Ferozepur
PROJECTS |
| Package |
Name |
Length
(Kms) |
Scope |
Status |
Target Date |
Pre - Construction Activities |
PSRSP/WB/
RH/1/NCB |
|
34.46 |
Pavement Rehabilitation + 2 x 1.5m gravel shoulders |
Work in Progress |
November 2008 |
1. Forest Clearance (Yes)
2. Relocation of Electric Utilities (On going)
3. Relocation of Sewerage utilities
(On going) |
PSRSP/WB/
RH/5/NCB |
|
24.70 |
Pavement Rehabilitation + 2 x 1.5m gravel shoulders |
Work in Progress |
November 2008 |
1. Forest Clearance (yes)
2. Relocation of Electric Utilities (On going)
3. Relocation of Water Supply Utilities (On going)
4. Relocation of Sewerage utilities (On going) |
PSRSP/WB/
PM/7/NCB |
|
30.27 |
Overlay - SDBC |
completed |
- |
- |
|
|
|