PSRSP/WB/
UG/2/ICB |
|
71.92 |
Ludhiana Malerkotla - Widening to 4 Lane + 2 x 1.5m paved shoulders including bypass at Pohir and Gill
Malerkotla Sangrur - Widening to 2 Lane + 2 x 2.5m paved shoulders |
Mobilization in Progress |
August 2010 |
1. Forest Clearance (yes)
2. Land Acquisation (On going)
3. Relocation of Electric Utilities (On going)
4. Relocation of Water
Supply Utilities (On going)
5. Relocation of Sewerage Utilities (On going) |