Punjab State Road Sector Project Division MOHALI
Central Works Division, PWD B & R, Mohali
PROJECTS |
| Package |
Name |
Length
(Kms) |
Scope |
Status |
Target Date |
Pre - Construction Activities |
PSRSP/WB/
UG/1/ICB |
|
39.53 |
Widening to 2 Lane + 2 x 2.5m paved shoulders including 6 kms of four laning from Kharar to Landran |
Mobilization in Progress |
December 2009 |
1. Forest Clearance (yes)
2. Land Acquisation (On going)
3. Relocation of Electric Utilities (On going)
4. Relocation of Water Supply Utilities (On going)
5. Relocation of Sewerage Utilities (On going)
|
PSRSP/WB/
RH/2/NCB |
|
37.30 |
Pavement Rehabilitation |
Work in Progress |
November 2008 |
1. Relocation of Electric Utilities (On going)
2. Forest Clearance
a. under Fatehgarh Sahib Division (yes)
b. under Roopnagar Division (yet to be received)
|
PSRSP/WB/
RH/6/NCB |
|
28.30 |
Pavement Rehabilitation |
Work in Progress |
December 2008 |
|
|
|
|